The path to a good weld
What each step means
You don't buy a WPQ in a vacuum. The card sits on a qualified procedure. Think of it like a kitchen: nine steps, from checking the groceries to serving the plate.
Proven ingredients make a trusted recipe. A trusted recipe still needs a qualified chef.
Material
The metal is what the spec says.
Check the label matches what's in the bag before anything gets cooked.
First. You don't weld until the metal is the metal.
Calibration
The machine is in tolerance.
If the dial says 350°, it has to be 350°. Otherwise the recipe is a guess.
Sits with material: before the first arc, and again on interval. Done at your shop.
$175 per welding machine · plus mileage at 72.5¢/mile
Coupons
The sample joint.
Cook it once, on purpose, so you can cut it open and see what happened.
The weld you test so the procedure can be proven.
School discount available
PQR
Procedure Qualification Record
What was actually run, and what it tested.
Exactly what went into the test batch, and how it came out when tested.
Sits after the coupon. TQT writes the record from the coupon. The procedure is qualified here.
Typically 5–7 days · Expedite Service 3–5 days or Rush Service 1–2 days available
WPS
Welding Procedure Specification
The written procedure the shop runs.
The written steps the kitchen follows every time, built on proven ingredients.
Sits on the PQR. Qualified by an accepted PQR.
$295 per WPS · typically 5–7 days
WPQ/WOPQ
Welder & Welding Operator Performance Qualification
The card that says this welder can run it.
Proof this cook can make the recipe. A great recipe still needs a qualified hand.
Sits on the WPS. Orbital operators qualify with a WOPQ. Fail NDT and you come back here.
From $150 per welder test · $250 orbital operator · school discount
NDT
Nondestructive Testing
Proof the weld is good.
Check the plate before it leaves the kitchen, without taking a bite out of it.
After production. Pass: you're done. Fail: back to WPQ to requalify.
Full day onsite + mileage · by the hour in our lab
Good weld
The destination. Released.
It left the kitchen and it's right. Released.
Then stay good: recalibrate and re-verify on interval.
The loops
The path isn't a straight line
Two things send you back.
Fail
NDT → back to WPQ
Retrain, requalify, re-inspect.
The plate gets sent back. The chef proves the dish again before it goes out.
Stay good
Good weld → back to Calibration & Material
Recalibrate, re-verify on interval.
Check the oven and restock the pantry on schedule, so tomorrow's dinner is as good as today's.
Not sure which step you're on?
Call us. We'll tell you where you are on the path and what's next.